Remote island and camp plants are often a long way from a service workshop. GUANYA WATER SOLUTION’s established support model for modular international projects is therefore built around three things that travel with the plant: a factory acceptance test, complete English documentation, and remote video guidance for the site team. On-site attendance is available when it is requested and scoped; it is not assumed in every equipment supply.
This article describes what that model does and does not include. It does not claim 24-hour on-site attendance or a permanent service partner in every country.
What is included after delivery
For a factory-integrated containerized or skid plant, the following support is part of the standard delivery model, unless a contract says otherwise:
- FAT records and a factory test video, so the site team can see the sequence the plant already ran before shipment
- An English operation and maintenance manual covering start-up, shutdown, routine maintenance, troubleshooting and alarm response
- English labels on operator-facing controls and required equipment identification
- Remote video assistance and operating guidance for the site team during installation, start-up and operation, including start-up readiness checks, operating questions and fault diagnosis
The aim is that, once the approved water and power interfaces are connected, the owner’s operators can start the plant according to the FAT-proven sequence without waiting for an overseas mobilisation.
What remote support can reasonably diagnose
Remote guidance is most effective when the site team can show, or read back:
- the current HMI or alarm list
- feed, operating and product pressures and flows, and product conductivity or TDS
- pretreatment differential pressure and any recent rinse or backwash history
- a view of the control panel, pump seals, cartridge housings and chemical dosing tanks
- recent changes in seawater quality, power supply or operator settings
With that information, many start-up, dosing, alarm and “will not start” issues can be isolated to an interface, a consumable, a setting or a genuine equipment fault. The spare-parts article explains how to order from the nameplate once the required item is identified.
Remote support cannot replace a correct site hook-up, a permitted concentrate discharge, a suitable raw-water supply, or qualified people on site. It also cannot inspect hidden mechanical damage that has no visible symptom or measured data.
What requires a visit
Physical attendance — installation supervision, on-site commissioning, classroom or plant-floor training, and annual or breakdown inspections — is a separate, optional service. It is quoted after the scope, dates, site access, travel and accommodation have been agreed, and the quotation states the number of engineers and service days.
A visit is typically justified when:
- the owner has asked for witnessed on-site commissioning or formal operator training
- a fault cannot be isolated from video, HMI data and photographs
- mechanical work on high-pressure pumps, membranes or structural items needs hands-on supervision
- a warranty inspection or contractual annual visit has been agreed in writing
Warranty, in outline
Warranty terms are confirmed in each contract. A typical framework used on modular export projects is: 12 months from signed site acceptance, provided acceptance takes place within six months after shipment, and in any event no later than 18 months after shipment. A longer period from acceptance is only by separate written agreement. Warranty covers manufacturing defects under normal operation. It does not usually cover consumables, chemicals, improper operation, unauthorised modification, incorrect site interfaces, or force majeure.
How to request support
Contact the export team at [email protected] with the system nameplate reference, a short description of the symptom, and, where possible, HMI screenshots or a short video. Use the same project channel already agreed in the contract (email or messaging) so the plant history stays in one place.
Companion articles: factory acceptance and commissioning; spare parts and consumables; chemical dosing and CIP; intake and brine discharge.