Project status · Shipped. Commissioning and operating results are not published as measured performance.
GUANYA WATER SOLUTION shipped a compact, skid-mounted seawater reverse-osmosis (SWRO) unit to an island tourism site in Malaysia. The rated product flow is 1 m³/h. At 20 operating hours per day, that is a planning figure of 20 m³/day. Actual daily output depends on feed conditions, operating hours, cleaning and downtime.
This capacity is widely requested for island hotels, resorts and similar coastal sites that need a dependable freshwater supply without a large civil plant. The Malaysia unit is a factory-assembled skid, packed in an export wooden crate and delivered to the island site. It is not a containerized plant, and it is not related to any larger quoted scheme.
The crated compact SWRO unit arriving at the island site in Malaysia. Project status: shipped.
Project overview
| Application | Water supply for an island tourism site in Malaysia |
|---|---|
| Water source | Seawater |
| Project stage | Shipped |
| Rated product flow | 1 m³/h |
| Planning daily volume | 20 m³/day at 20 operating hours |
| Equipment form | Skid-mounted SWRO, stainless-steel frame, export wooden crate |
Rated design figures
The figures below are equipment-specification values for this shipment. They are not published field measurements from the operating plant.
| Parameter | Specification |
|---|---|
| Rated product flow | 1 m³/h |
| Salt rejection | 97% |
| System recovery | 31% |
| Feed-water TDS | ≤ 36,000 mg/L |
| Product-water TDS | ≤ 700 mg/L |
| Operating pressure | 3.5–5.5 MPa |
| Installed power | 10 kW |
Process configuration
The skid is a complete treatment train assembled and tested at the factory:
- Pretreatment: quartz-sand filter, activated-carbon filter, and 5-micron cartridge filtration
- High-pressure seawater RO, arranged as a 2:1 array with six 4040 seawater membranes in 1,000 psi FRP pressure vessels
- Antiscalant dosing and ultraviolet disinfection of the product water
- Conductivity monitoring on the feed and product lines, with pressure protection and a control panel with a variable-frequency drive
Raw-water and product-water storage tanks were in the owner’s scope. After delivery, time to first water depends on site conditions: intake, power, tank hook-up, concentrate discharge and commissioning. This page does not promise a fixed number of hours from arrival to water.
Factory photograph of the 20 m³/day compact skid-mounted SWRO. This is a factory view of the equipment type, not a photograph of the installed plant in Malaysia.
Pretreatment vessels and the 4040 membrane array on the compact skid, photographed in the factory.
Why this page is labelled “shipped”
The unit has left the factory and has been delivered to the site. This page does not present commissioning results, energy consumption, or product-water quality recorded in operation. If measured operating data are later approved for publication, the status line can be updated. Until then, treat the tables above as the design basis of the shipped equipment.
Related reading
- 20 ton/day compact seawater desalination system
- Containerized seawater desalination for a Fiji island resort
- 205 L/h mobile SWRO for Maldives overwater hotels
- Factory acceptance and site commissioning for containerized SWRO
- Seawater intake and brine discharge for island SWRO
Frequently asked questions
What was shipped to Malaysia?
GUANYA shipped a compact, skid-mounted seawater reverse-osmosis unit with a rated product flow of 1 m³/h (a planning figure of 20 m³/day at 20 operating hours) to an island tourism site in Malaysia.
Is this an operating performance case?
No. The project status is shipped. Commissioning and operating results are not published as measured performance.
What are the design water-quality figures?
The equipment specification is feed-water TDS up to 36,000 mg/L, product-water TDS of 700 mg/L or less, 97% salt rejection and 31% recovery. These are design figures, not published field measurements.
What does the owner provide on site?
Feed and product storage tanks were in the owner’s scope. Time to first water still depends on intake, power, tank hook-up, concentrate discharge and commissioning. No fixed number of hours is promised.