GUANYA WATER SOLUTION has prepared a containerized seawater reverse-osmosis (SWRO) design for a coastal site in Greece. The nominal design production is 1,000 m³/day, arranged in two customized 40 ft high-cube containers. The work is at design and quotation stage (April 2026). The plant has not been manufactured or commissioned by GUANYA, and this note is not an operating or shipped-plant reference. The site and client names are withheld.
Status: Design proposal and quotation | Country: Greece | Duty: Coastal seawater desalination | Design capacity: 1,000 m³/day in two 40 ft high-cube containers
Design basis (proposal stage, not measured operation)
| Item | Design-basis value |
|---|---|
| Country / setting | Greece, coastal site (identity withheld) |
| Nominal product capacity | 1,000 m³/day |
| Package | Two customized 40 ft high-cube containers |
| Design feed TDS | Seawater, ≤ 36,000 mg/L, subject to confirmed local seawater analysis and temperature |
| Design recovery / rejection | 42% design recovery; 97% design salt rejection |
| Design product TDS | ≤ 700 mg/L (calculation figure 200.1 mg/L on the quotation sheet, not a field measurement) |
| Working pressure / power | 3.5–5.5 MPa; 400 V electrical basis |
| Main process stages | Feed pumping, quartz sand filtration with automatic multi-way valves, 5 µm cartridge filtration, high-pressure SWRO (2507 duplex pumps and 8040 membrane vessels), instrumentation and controls |
| Status | Design and quotation — not shipped, not commissioned |
Figures above come from the April 2026 quotation sheet and represent design-basis targets rather than measured operating logs. Factory assembly and pre-testing are standard; time to first water depends on intake, power, storage and site hook-up.
What this page is not
It is not a shipped or operating desalination plant in Greece, and it does not promise a fixed commissioning duration or measured energy consumption.
Related reading
Frequently Asked Questions
Has this 1,000 m³/day Greece plant been shipped?
No. The status is design and quotation (April 2026). It has not been manufactured or commissioned by GUANYA.
How many containers are in the design?
The quotation arranges the 1,000 m³/day plant in two 40 ft high-cube containers.
Is 200.1 mg/L a measured permeate reading?
No. It is a design calculation note on the quotation sheet; final permeate TDS depends on actual seawater salinity, temperature and confirmed post-treatment.